east campus

The East Campus project is moving along as scheduled. As a reminder, the East Campus project is part of the long-term facility plan to make room for a new primary building attached to the current elementary budling. Following are items visible regarding the project:

Softball

  • Dugout walls are complete

  • Field being prepped for turf

  • Fence posts installed

  • Formation of the field is recognizable.

Baseball

  • Import of dirt continuing

  • Footings for press box and dugouts staked out

  • Scoreboard being delivered soon

Tennis Courts

  • Grading in progress

  • Lights on property

Concession Stand

  • Block walls 90% complete

  • Floor finished

  •  Trusses being prepped to install

*All materials are on site and the pace of project is moving per established timelines.